Fort Smith reports progress on sewer rehabilitation project 23-19-C1

Fort Smith, Ark. – The City of Fort Smith announced progress on Project 23-19-C1, part of the Consent Decree program aimed at addressing sanitary sewer issues.

The project involves replacing or rehabilitating 8,715 linear feet of sewer mains by the open-cut method, 1,720 linear feet of sewer service lines, 85 service cleanouts, 130 point repairs, and 95 manholes.

According to the city’s latest update, 5,394 linear feet of sewer pipe have been remediated by open-cut, 1,346 linear feet of service lines completed, 85 service cleanouts finished, 92 point repairs completed, and 78 manholes removed and replaced.

The total value of work completed so far is $5,246,782.19. Officials confirmed the project remains on schedule, with an expected completion date of January 30, 2026.

More information on this and other Consent Decree projects is available at fortsmithar.gov/consentdecree.